FLEMINGTON -- Heavy rainfall has delayed PennDOT's plans to complete final paving at the Flemington Bridge along Route 150 by one day.

Work to preserve this bridge, which spans Bald Eagle Creek in Bald Eagle Township, started in June 2023 and will improve the overall condition rating of the structure from fair to good.

The contractor planned to begin milling the roadway at the bridge Thursday, but recent weather forced a delay. It will now mill the roadway tomorrow and pave Monday, April 8. Flaggers in the roadway will provide traffic control during daylight hours on Friday and Monday. The work remains weather dependent.

Upon completion, placing an epoxy overlay treatment over the bridge surface will be the last work remaining on this contract. PennDOT anticipates this work to take place sometime in May and will issue an update before the contractor starts that work.

Two other structures saw work under this contract. One is a Route 150 bridge spanning Chatham Run in Dunnstable Township. The other is a Route 220 bridge spanning Route 2006 and Fishing Creek in Lamar Township. Work on those bridges is complete.

HRI, Inc. of State College, PA, is the contractor for this $3.5 million job.

Motorists are encouraged to "Know Before They Go" by checking conditions on more than 40,000 roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information, and access to more than 1,000 traffic cameras.