MILL HALL -- Bald Eagle Township supervisors approved spending up to $10,000 for materials to address two problem areas along Bald Eagle Mountain Road during their Nov. 16 meeting, following continued concerns about the results of a recently completed paving project.
The discussion centered on multiple sections of the road where residents and supervisors have raised concerns about the grading and drainage following the work.
Supervisors discussed a proposal from the contractor, Glenn O. Hawbaker, to correct the two most problematic areas, identified as the sections near residents' properties. Under the proposal, the contractor would provide the labor, while the township would pay for materials.
The proposed work also includes correcting the painted center lines on the road.
Vice chairman Ken McGee questioned why the township should have to pay for corrections to work that was not completed properly in the first place.
"Why are we paying somebody for them to fix their screw-up? They should be doing it the correct way," he said.
McGee expressed additional concern about the condition of the road, noting that the paving appeared to have made some areas worse rather than improving them.
"The road was flat. Overlying this road, overlying the original road, we've made it worse. We did not make an improvement," McGee said.
Concerns included areas where the road's slope appeared to exceed the 3% cross-slope requirement, water collecting near driveways and difficulty with drainage along the roadway.
Township representatives discussed the challenges of proving the condition of the road before construction, noting that there was no formal documentation of the previous grades.
The contractor had previously discussed correcting the areas, with the township being responsible for materials and the contractor providing labor. The estimated cost was discussed as approximately $5,000, with a maximum of $10,000.
Supervisors ultimately agreed that addressing the two worst areas was the most practical way to move forward rather than pursuing a more extensive dispute.
"I think this is a path of least resistance," Chairman Steve Tasselli said.
A motion was made and seconded to have the contractor correct the two problem areas for a cost not to exceed $10,000 for materials only, including the line painting. The motion passed.
UCC Appeals Board discussion
Supervisors also continued discussing the possibility of sharing a Uniform Construction Code (UCC) Appeals Board with Mill Hall Borough.
Mill Hall originally decided to vote against the use of a shared appeals board during their October council meeting as their current members may not have the knowledge needed for larger industrial appeals.
The township has continued working to establish an arrangement that would allow it to use the borough's existing board rather than create and maintain a separate appeals board.
Tasselli reported speaking with Mill Hall Borough Council members Tony Walker and Derek Caris about the proposal. The township indicated it would be willing to pay applicable fees associated with using the borough's board.
"The bottom line is, this is the most expedient way," he said, explaining that the township would prefer to work through an intergovernmental agreement.
The appeals board was brought up following a letter from Avery Dennison which included a pending appeal involving a handrail at a construction project. The handrail was designed at a length that interferes with access to a doorway, and the applicant is seeking permission to shorten it by 12 inches.
The township solicitor Frank Micello explained that the appeal was filed Oct. 12 and that the hearing would need to be advertised by approximately Dec. 8 to meet the applicable requirements. If the required hearing is not held within the established 60-day period, the request could be considered approved by default.
Micelli explained that the township would need to adopt a resolution to formalize an agreement with Mill Hall Borough.
Supervisors said they are waiting for Mill Hall Borough to revisit the proposal before moving forward with the agreement at their meeting on Nov. 23. A possible special meeting in December was discussed to address the resolution if the borough agrees.