LOCK HAVEN -- Lock Haven City Council took another step towards the renovation of City Hall.
On Monday night, council reviewed schematics for the renovations -- which focuses mainly on moving the city's police department to the second floor -- with staff and Arlan Hollinger, representing Buchart Horn Architects.
City Planner Abbey Kling said the schematics, and the proposed bidding process, were a step before approval of any final plans and placing the project out for bid.
The schematics presented included the second floor renovations for the police department along with some renovation in the basement -- which currently houses the police officers -- and first floor renovations.
Kling noted the basement and first floor renovations could be adjusted and are reflected in the bidding process provided for council's consideration.
The bidding structure focuses on the second floor renovation with three alternate bidding options that could be included.
The estimated cost for the base-bid of second floor renovations, including HVAC, electrical and ceiling work, is about $2,388,400. The city currently has roughly $2.5 million budgeted for the renovations.
The first of the alternative bids is the renovation of the first floor to include a public lobby with restrooms, access to council chamber and reconfiguration of the water and finance offices to provide service window access in the lobby.
The second alternative would be the replacement of exterior windows on the second floor at an additional cost of about $115,000.
The third alternative would see windows replaced on the second and first floors at an estimated cost of $220,000.
Cyndi Walker, who leads the city's building and code office, noted the alternatives can be added with the base-bid or bid out in the future, depending on the costs.
"It's a comprehensive bid package that is going to be put out. So every person who submits a bid is going to bid it as the base-bid, alternate one, alternate two and alternate three. That way you can see what every contractor is offering and then it's easy to be able to pull out what doesn't work, move around what is affordable," Walker said.
Kling said staff were looking for approval of the schematics and the bidding structure.
Mayor Joel Long, who is a member of the building renovation committee, said the structure was something discussed in previous meetings to help mitigate excessive costs.
"I think as we discussed in the building committee meetings, we put it out there and we can always say 'we can't do this part right now.' That doesn't mean we let the ball drop and it never happens. But trying to line up and get as much as we can done with the funding we have currently," he said.
Following discussions, council unanimously approved the schematics and bidding structure.
Also during Monday's meeting, council reviewed an update for current renovations to City Hall.
According to information provided to council members, multiple action items were addressed regarding the renovation projects.
This included relocating police files and evidence from the basement to the second floor; receiving cost estimates for lead paint and asbestos abatement; beginning the design process for police locker rooms with Buchart Horn; receiving the schematic designs that were reviewed this week and the consideration of window replacements, which were featured in the approved bidding structure.