MILL HALL -- Mill Hall Borough Council discussed several maintenance and equipment needs and upcoming holiday preparations during their meeting Nov. 24.

Council approved a $750 annual maintenance agreement with Shade HVAC for cleaning two mini-split systems twice a year and the borough's Rinnai heaters in the maintenance shop once annually.

The borough had also received quotes from other providers, including Redmond's at $1,000 and Complete Climate Control at $1,719.

After reviewing the quotes, council agreed to approve Shade HVAC at the quoted price, noting this will be the borough's first contract with the new company.

Council also continued discussion on purchasing a tar buggy, with SealMaster resubmitting a quote of approximately $79,000. An updated quote from Crafco was not yet available, though borough officials anticipated it could be comparable, with some additional features potentially increasing the price.

Council members discussed coordinating with Castanea Township and Lamar Township, both of which have expressed interest in a shared equipment agreement, to further discuss the purchase during the December Sewer Highway Committee meeting.

Council approved a motion to have borough representatives reach out to the other municipalities to arrange the discussion.

Borough staff reported that leaf collection was nearing completion, with approximately 125 bags collected during the final scheduled pickup. The dumpster will remain available through the following Tuesday in case additional leaves need to be collected.

The borough plans to install a Christmas tree at the World War II Memorial, with the tree donated by Slopey's Tree Farm and lights donated by council members. Borough crews planned to install the tree the following week, weather permitting, ahead of the holiday lighting season.